Derby Data Centre Blog

Hall 2 DC1 Live

Wednesday, June 30th, 2010

Hall II is now LIVE!

Tuesday, August 5th, 2008

We are please to announce that Hall I is now LIVE and has its first set of paying customers in an operational…

This is an exciting time for Node4, with the success of Hall I in DC2 and now with the extra capacity of 136 racks , we are firmly on course to becoming one of the leading high qaulaity co-location suppliers in the UK..

All the racks have a minimum 4Kw power rating withsome racks having the abbility to take 8Kw, with A+B resiliant feeds.

The Spec of DC2 is below Or download the datasheet

Node4 Data Centre Datasheet
Node4 Data Centre Datasheet

Features

  • Flexible packages and options
  • State of the art Data Centre
  • Ideal if you already have the best server for your requirements
  • On-site technical support team
  • Convenient central location in the Midlands, minutes from the M1
  • (6,000 sq ft) net capacity
  • 2 separate Data Halls
  • 24 Hour Manned Security
  • 24 Hour Technical Support
  • 3 × N+1 Generators
  • 4 × 300kVA Riello UPS (N+1)
  • Diverse Connection to National Grid
  • N+1 Stultz DX Cybercool Air Conditioning Systems
  • FM200 Fire Suppression
  • CCTV & Intruder Alarms
  • Up to 32A Twin supplies Per Cab
  • Diverse Fibre Entry
  • BT, Kingston Comms Fibre
  • Multiple T1 Carriers for Internet Transit
  • 14.5kN/m² raised floor system
  • Optional SAN back-up service

Hall II Update

Monday, June 2nd, 2008

Work has been progressing well in our second data hall.

The raised access floor is now installed and we have 2 aircon units installed and tested.

You can see the 2 Stulz aircon units at the far end of the room. 2 more units will be fitted at that end of the room with a further 2 at the opposite end.

Hall 2 will have 6 rows of between 21 and 23 racks, giving a total of 134 racks. There is also the option of caged areas (although this will reduce overall capacity). The racks are laid out in a standard hot/cold aisle system to ensure the best airflow around the racks.

Under each cold aisle are the dual power supply tracks from our UPS and generator backed power feed. Upto 32A of power can be fed into any cabinet, with the option for a second, redundant feed in the same rack.


The FM200 fire suppression system is also being installed. Hall 2 is physically separate from hall 1, so the suppression system will operate independently as will the air-conditioning and power feeds.


If you have any questions about the datacentre or any of our products or services, please contact our sales team on 0845 123 2222 or sales@node4.co.uk


Work on hall II begins!

Saturday, April 5th, 2008
We’ve filled Hall 1 and started work on Hall 2
Hall 2 is bigger than hall 1 with a capacity of 136 racks. taking the total capacity to 220 racks.

We are currently connecting up our additional UPSs and laying the electrical tracks ready for the raised floor to go in.

Hall 2 will have 7 aircon units in total, providing N+1 cooling for all 136 racks

We are already taking orders for space in this part of our facility, so call our sales team on 0845 123 2222 for more information.